01/07/2009 07:39:53
 
OIL & GAS
Loaded out Topside of Ca Ngu Vang WHP

06/10/2008 15:06:20

Vietsovpetro Joint Venture celebrated the topside load out ceremony for the Ca Ngu Vang Field project on 07 June at VSP port.

Vietsovpetro was the EPC contractor for the Topside of Ca Ngu Vang WHP under the contract between Hoan Vu JOC and Vietsovpetro Joint Venture.

The topside consists of 4 jackets with 56m water depth, over 90-ton weight; the topside block has a 780-ton topside primary structure and a 315-ton topside module.

Previously, its jacket had been loaded out and installed at Ca Ngu Vang field on 07 April 2008.

After the topside was sailed away to the sea and finished installation at Ca Ngu Vang Field, this will be the first oil rig of the field, it is officially started exploitation on 06 July 2008 as scheduled with the expected production of about 20,000 oil barrels/day.

Nhut Thanh
Print
 
NEWS MORE
Vietnamese “high quality” employees get US$3,000 – 5,000 paid monthly in field of oil and gas industry (03/06/2008)
Successfully loaded out Topside of Phuong Dong Oil Rig Platform (29/05/2008)
PetroVietnam fertilizer signs import deal with Qatar fertilizer (18/05/2008)
Vietsovpetro Joint Venture (VSP): rise up in oil and gas industry field (13/05/2008)
Work begins on Vietnam’s $6 billion oil refinery (11/05/2008)
Vietnam to start building $6 billion oil refinery (06/05/2008)
PetroVietnam proposal fuels Oman cooperation (18/04/2008)
Petroleum Industry to Enjoy More Open Policies (31/03/2008)
Protection in oil and gas projects (24/03/2008)
PetroVietnam imports gas to plug shortage (14/03/2008)
Next

 

 
Search with Google
 
Back to top Add to Favorites Set to homepage
© BariaVungTau Newspaper Online